Ramaco Resources released an initial assessment by Hatch for its Brook Mine rare earth and critical minerals project, detailing process, capacity and cost estimates.

Key Highlights:

  • Hatch delivered an Initial Assessment (July 28, 2026) for Brook Mine covering process, mass balance and AACE Class 5 cost estimates.
  • Base-case throughput set at 1.3 million dry mt/yr ROM with target CMO-equivalent production of 574 dry mt/yr.
  • Updated HPA target increased to 11,848 mt/yr; HPS target 18,617 mt/yr and original HPA basis used for site layout.
  • Class 5 CAPEX equipment supply noted ~421 M USD (used to derive maintenance); OPEX estimated at 150.7 M USD/yr (excl. contingency, G&A).
  • Process centers on carbo-chlorination with projected Ga and Ge recoveries of 94% and 84%; further test work and Class 4 estimates planned.

Original SEC Filing:

This is an AI-powered summary. It may contain inaccuracies. Consider verifying important information with the source. Please note this summary is solely based on documents filed with the SEC.