Soluna announces inclusion in the Russell 3000 and operational progress across Dorothy, Kati and other projects; first quarterly earnings call set for Aug 13.

Key Highlights:

  • Added to the Russell 3000 and Russell 2000 Value Index, broadening visibility to index-aware investors.
  • Scheduled first quarterly earnings call for 5:00 pm EDT on August 13, 2026 to review Q2 results.
  • Project Dorothy sites operating at full capacity despite increased 4CP curtailments; deployments continuing.
  • Kati 1: K1A operations steady; Phase 2 Soluna MDCs (9 MW) substantially complete, Phase 3 (14 MW) ahead of schedule.
  • Kati 2 and Dorothy 3 progressing: Kati 2 GC selected, design ~50% complete, LOI signed with a potential tenant; Dorothy 3 schematic design and surveys underway.

Original SEC Filing:

This is an AI-powered summary. It may contain inaccuracies. Consider verifying important information with the source. Please note this summary is solely based on documents filed with the SEC.