Hyperscale Data announced plans for a Michigan data center buildout with 20 MW contracted (10 MW to be energized within 90 days, additional 10 MW within 180 days) and broader campus and robotics expansion potential.
Key Highlights:
- Contracted 20 MW of critical IT load at Michigan; first 10 MW targeted to be energized within 90 days, next 10 MW within 180 days.
- Michigan site has up to ~52 MW potential critical IT load (20 MW contracted plus 32 MW at customer's option), subject to securing additional power.
- Company plans campus expansion—acquiring ~48.5 acres to grow Michigan campus to ~83 acres with long-term potential into multi‑hundred MW capacity.
- Outlines non‑grid natural gas and incremental grid options, and contemplates up to ~125 MW at a primary site pending definitive arrangements and approvals.
- Planned robotics facility to support teleoperated data collection, model training (1.5–3M training hours in 18–24 months), pilot deployments and humanoid robotics sales.
Original SEC Filing: